Skip to main content
Gordon Rees Scully Mansukhani, LLP. logo.

Boston Team Secures Massachusetts Appeals Court Victory Affirming Dismissal of Architect from Declaratory Judgment Action

Boston Senior Counsel Shaun Loughlin and Associate Isabel Wilker recently obtained an affirmance of dismissal for a firm client in the Massachusetts Appeals Court in litigation involving a subcontractor’s assertion of public bid violations against an architect, town, and general contractor. Loughlin and Wilker prepared the appellate brief, while Loughlin appeared for oral argument.

The matter involved the design and construction of a new fire department/public safety building in a Massachusetts town. GRSM’s client, an architect, contracted with the town to prepare the design documents released to potential bidders. During the bid submission process, the architect issued multiple addenda that refined and clarified aspects of the design documents in response to bidder questions. One addendum confirmed that the masonry subcontractor would be responsible for certain exterior stone work depicted in the landscape design drawings.

The plaintiff ultimately secured the masonry subcontract and, shortly after the project began, disputed responsibility for the exterior stone work after the general contractor requested associated materials. The plaintiff contended that the work fell outside the masonry scope because it appeared in the landscape plans and specifications rather than the masonry plans and specifications, prompting a dispute over whether the architect’s pre-bid addenda assigning responsibility for the work had been incorporated into the plaintiff’s bid submission.

After the town rejected the plaintiff’s requested change order, the plaintiff filed a declaratory judgment action in Superior Court against the architect, general contractor, and town. The plaintiff sought declarations that the defendants violated Massachusetts public bid statutes by failing to incorporate the stone work into the masonry plans and specifications and that the plaintiff was entitled to additional compensation for performing the work.

Loughlin and Wilker successfully moved to dismiss the claims against GRSM’s client, arguing that the architect was not a “necessary party” under Massachusetts’ declaratory judgment act because the architect had no contractual relationship with the plaintiff and lacked authority to issue a change order. The plaintiff argued the architect was a necessary party because it prepared the plans and specifications at issue and could potentially face negligent misrepresentation claims in future litigation.

The Appeals Court affirmed the dismissal, agreeing with both the GRSM team’s arguments and the Superior Court’s ruling. Specifically, the Appeals Court held that the plaintiff’s claims “would have no legal impact” on the architect and further determined that the possibility of future litigation against the architect “has no bearing on the conclusion” of the declaratory judgment claim.

This result highlights GRSM’s Construction Practice Group’s deep understanding of the contractual rights and obligations among project participants in both public and private construction matters, as well as the team’s ability to translate that practical industry knowledge into effective advocacy on technically complex legal issues.

The matter also reflects one of several favorable appellate outcomes achieved by GRSM’s Boston office over the past year, underscoring the firm’s growing and successful presence in the Massachusetts appellate courts.