In order to preserve your right to payment, you must satisfy the contractual requirements supporting a change order for the increased costs or time due to the delay. The key to the successful presentation of change order claims is educating your team on the following:
1. NOTICE
-
Provide ALL information available.
-
If certain information is not yet available, state that the information will be provided when available.
-
Reserve all rights to amend and submit additional information.
-
Request both an increase to the Contract Sum and Contract Time.
-
Does it require certified mail?
-
Is email sufficient?
-
If email is not proper notice, be sure to issue via the required method in addition to email.
-
IF YOUR CUSTOMER DOES NOT ALLOW A TIME EXTENSION OR REJECTS YOUR NOTICE, respond and provide further notice that you consider the rejection a “Constructive Acceleration” and will be forced to incur overtime and other potential labor, material, and equipment costs.
2. ENTITLEMENT
-
Prepare and submit an entitlement packet that demonstrates your legal and factual entitlement to a change.
-
Legal Entitlement: Review your contract for clauses that would allow for the recovery of delay and/or acceleration costs, or look for common law options that may invalidate no-damages-for delay clauses such as the delay was “beyond the contemplation of the parties” or if you were “constructively accelerated”.
-
“Excusable Delay”
-
Delay
-
God (Acts of God)
-
Epidemic
-
Quarantine
-
No Damages for Delay
-
“Time Extension”
-
“Sole Remedy”
-
“Accelerat” – Acceleration damages are different from delay damages. If you request a time extension and are not granted the extension, you may have a claim for directed, or constructive acceleration.1
-
Track and document each day of delay through schedules, time sheets, daily reports, payroll documentation, or other project records.
-
Provide updated entitlement packet to support change order request as information is updated.
3. DAMAGES
-
Increased cost of materials
-
Increased cost of labor
-
Increased cost of equipment rental charges
-
Storage of materials
-
Additional supervision or field costs for the extended duration
-
Costs associated with de-mobilization and re-mobilization
-
Lost overhead and profit
-
Costs for extended general conditions, equipment costs, or rental costs
-
Additional bond or insurance premiums
-
Tax implications
-
Use daily time cards, certified payroll, daily reports, or a separate phase code in your job cost accounting to track actual labor delays and impacts.
-
Materials – Gather notices from suppliers relating to increased costs and delays. Gather the invoices and checks showing payment for any increased costs.
-
Equipment – Gather proof of down-time hours through daily time cards, certified payroll, daily reports, or a separate phase code in your job cost accounting to track labor.
-
Overhead and Profit – Cite to contract section setting forth allowable OH&P on changes.
-
Storage, Subcontractor and Vendor Costs – Produce invoices and proof of payment for increased costs resulting from delays and acceleration.
4. DON’T WAIVE YOUR CLAIMS
-
Follow dispute resolution procedures in the contract (including time provisions).
-
Be aware of statute of limitations to file lawsuits.
-
Bond and lien claim deadlines.
For questions, contact Denise M. Motta.
1 A claim for constructive acceleration arises where (1) there is an excusable delay; (2) you properly request a time extension; (3) the request for extension was denied; (4) you were ordered to complete the project by the original completion date despite the excusable delay; and (5) you accelerated performance and incurred additional costs. A claim for directed acceleration arises where (1) you are ordered to accelerate (perform in a shorter period than originally allowed by the contract schedule); (2) the delays prompting the acceleration were excusable; and (3) you accelerated performance and incurred additional costs.